Year 2024
Type Industrial insulation: boilers and furnaces

Industry: Energy

Country: Poland, Włodawa

Year of implementation: August - September 2024

 

Task:

  • to carry out the lining of a 9 MW biomass boiler at the CHP plant in Włodawa

 

Implementation:

During the implementation of the project, our specialists performed the following works:

  • installation of fireproof bricks with a total weight of 11.2 tons;
  • installation of fireproof concrete with a total weight of 5.7 tons;
  • fireproof insulation with a volume of 28 m3.

The project involved 8 specialists from Inventum Polska.

 

Results:

The works were carried out in accordance with the applicable quality standards, requirements of the technical documentation, within the assumed time frame and taking into account the specifications and guidelines provided by the client.