Year
2024
Type
Industrial insulation: pipelines
Industry: Energy
Country: Poland, Poznań
Year of implementation: November - January 2024/25
Task:
- to perform insulation work on industrial pipelines in the engine room of a combined heat and power plant with an area of approximately 1,800 m2 in Poznań
Implementation:
Our specialists performed a number of insulation works:
- installation of 80-100mm thick mineral wool insulation;
- installation of an aluminum sheet casing (1050A);
- installation of sheet metal flashings.
The installation works, including the construction of the structure, installation of mineral wool and installation of sheet metal, were carried out by our team of 6 qualified employees.
Results:
The work was carried out in accordance with high quality standards, in accordance with technical requirements, within the established deadlines and taking into account the individual expectations of the client.